Home NewsNISO Restores Transmission Lines After Grid Disturbance

NISO Restores Transmission Lines After Grid Disturbance

by Torkuma Gbor
0 comments

The Nigerian Independent System Operator (NISO) has announced the restoration of all transmission lines affected by a grid disturbance on Friday, November 20.

‎‎NISO disclosed this in a statement issued in Abuja on Friday, clarifying that the incident did not amount to a collapse of the national electricity grid.

‎‎According to the system operator, the disturbance was caused by the tripping of some transmission lines, which resulted in electricity supply disruptions in parts of the country.

‎‎It explained that the Omotosho–Ikeja West transmission line tripped at 12:34 p.m., causing a significant drop in electricity supply within the Lagos Complex.

banner

‎‎The operator added that at 12:50 p.m., the Ihovbor–Oshogbo transmission line also tripped, alongside the Benin–Egbin and Ihovbor–Ajaokuta transmission lines, leading to further load losses in some parts of the country.

‎‎NISO said relevant operational teams, working in collaboration with the Transmission Company of Nigeria (TCN), immediately activated emergency response measures to stabilise the grid and restore the affected lines.

‎‎It confirmed that all the affected transmission lines had been successfully restored to normal operation by 2:49 p.m. on Friday.

‎‎The system operator reiterated its commitment to maintaining grid stability, coordinating electricity system operations and ensuring the reliable and secure operation of Nigeria’s national grid.

‎‎It also urged members of the public to rely on official statements from NISO for accurate information regarding developments in the national electricity grid.

‎‎(NAN)

‎

‎