The Federal Government has engaged and trained approximately 6,500 Nigerians for various construction activities on the ongoing Kano-Katsina-Maradi railway project.
The Permanent Secretary of the Federal Ministry of Transportation, Funso Adebiyi, disclosed this during an inspection of the project at the Kazaure construction site in Jigawa State.
Adebiyi, in a statement issued in Abuja on Saturday and signed by the ministry’s Assistant Director of Press and Public Relations, Mrs Osima Seddon, said only about 200 of the 6,500 workers currently involved in the project were expatriates.
He explained that the locally recruited workers would be retained after the completion of the project to enable Nigerians to operate and manage the railway infrastructure.
The permanent secretary also acknowledged the contributions of the Federal University of Transportation (FUT), Daura, Katsina State, towards providing specialised training and developing local manpower for the railway sector.
He said the first phase of the project, covering the Kano-Dawanau to Katsina section, was expected to be commissioned in December, while construction would continue on the remaining sections connecting Katsina to Jibia and Maradi in the Niger Republic.
Giving an update on the project, Adebiyi said about 650,000 of the 800,000 concrete railway sleepers required had already been produced at the construction yard.
He added that most of the materials needed for the project, including railway tracks and reinforcement materials, were already available at the site, while the required formwork had also been completed.
According to him, workers are currently assembling and coupling railway tracks towards Maradi, while the new executive rail line is expected to be completed within 10 days.
Adebiyi described the approximately 400-kilometre Kano-Maradi railway project as considerably longer than the Abuja-Kaduna and Kaduna-Kano railway corridors, which span 189 kilometres and 203 kilometres respectively.
On cross-border operations, he disclosed that the Federal Government had resumed discussions with the Niger Republic’s Ministry of Transportation to address security, immigration and customs requirements.
He said the discussions were intended to facilitate the movement of construction equipment, machinery and personnel between the two countries to ensure the timely completion of the remaining sections.
Meanwhile, the Vice-Chancellor of FUT Daura, Prof. Umar Katsayal, commended the permanent secretary and his team for visiting the project site, describing the engagement as an opportunity to strengthen the ministry’s support for the university.
Katsayal added that the visit would also encourage closer collaboration between the university and companies involved in railway construction and the provision of essential infrastructure, particularly signalling and communication systems.
(NAN)